Verona

Relamping and trigeneration intervention

Lösung

The intervention involved the rehabilitation of the roof (17,500 m³) and the installation of a photovoltaic system with a peak power of 999 kW and a trigeneration system consisting of a cogeneration module with 1,013 electrical kW and 969 thermal kW, combined with an absorption chiller with a cooling capacity of approximately 600 kW. This made it possible to produce energy on site and to achieve greater overall efficiency, being able to satisfy electrical, thermal and refrigeration needs at the same time, while avoiding the emission of over 1,300 tons of CO2 per year.

Standort


Verona
Auftraggeber

FEDERAL MOGUL ITALY S.R.L.

Gebäudetyp

Relamping and trigeneration

Realisierung
Standort
Verona